Portage Public Schools dives into second year of construction

Construction of Portage Central Natatorium, Portage North Middle School and Portage Northern's Huskie Stadium began in 2017 and continues to make major progress in 2018. Additionally, site preparations for the new Portage Central Middle School have officially begun.

Portage Central Natatorium

  • The pool is being water tested, a process that involves filling it up 1/3 at a time and waiting for 24 hours between each fill, to ensure there are no leaks.
  • Mechanical equipment for the new pool has been delivered and is ready for installation.
  • Taken in February, scaffolding was installed above the pool so crews could get to work on sound and lighting.
  • Also taken in February, crews worked above scaffolding to install sound panels, fabric ductwork, lights and paint the precast Ts.

Portage North Middle School

  • A concrete pump pours the mechanical penthouse floor
  • The concrete crew works on the mechanical penthouse floor
  • Masons build the south wall of the new gymnasium

Portage Northern's Huskie Stadium

  • Compaction around the goal posts and safety netting is complete. Crews finish the home team bleacher installation. The nearly complete concession building is being painted.
  • Long jump pits are filled and score board posts set. The stock pile of fines in the background will be spread on the field with a laser grader, on top of the 7" base that has already been laid. The base of the field is being leveled to ensure compaction, in preparation for turf installation next week! Home team lockers are in place. Next up, sealing and applying a rubber base to the floors.

In Other News

062 Park Elementary v1 1080 00 01 32 10 Still014

Hudsonville Park Elementary…

Hudsonville Park Elementary Construction Tour

Join Project Superintendent Ethan Elzinga and Assistant…
061 Rockford Ribbon Cutting v1 1080 00 00 10 17 Still002

Rockford Edgerton Trails Ribbon Cutting

Rockford Edgerton Trails Ribbon Cutting

Rockford Public Schools has officially cut the ribbon and…
01 BC Heritage Elementary Ribbon Cutting v1 1080 00 00 10 22 Still003

Byron Center Heritage Elementary Ribbon…

Byron Center Heritage Elementary Ribbon Cutting

O‑A‑K recently celebrated the grand reopening of the newly…
059 GRPM Safety FINAL 1080 00 01 02 17 Still010

GRPM Safety Walkthrough

GRPM Safety Walkthrough

Jobsite walkthroughs are an important part of O‑A‑K's…
Tobler O A k Team

Owen‑Ames‑Kimball Celebrates Ribbon…

Owen‑Ames‑Kimball Celebrates Ribbon Cutting of Franklin Park Elementary

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…
01 St Paul Ground breaking v1 00 01 12 07 Still014

St. Paul the Apostle Middle School and…

St. Paul the Apostle Middle School and Parish Commons Addition Ground Blessing

St. Paul the Apostle Catholic School recently celebrated a…
Sawatzky Taylor

Owen‑Ames‑Kimball’s Taylor Sawatzky…

Owen‑Ames‑Kimball’s Taylor Sawatzky Appointed to FGCU Alumni Association Board of Directors

Taylor Sawatzky, Director of Strategic Development at…
June 2024 New Hires

O‑A‑K Welcomes 14 New Employees

O‑A‑K Welcomes 14 New Employees

(Grand Rapids, MI) June 25, 2024 – Owen‑Ames‑Kimball…
00 Stills Pull 00 02 39 16 Still004

O‑A‑K Kalamazoo Celebrates 10 Years

O‑A‑K Kalamazoo Celebrates 10 Years

10 years ago, O‑A‑K increased our presence in Southwest…
Spring Lake BOE O A K TMP 4

Construction at Spring Lake High School…

Construction at Spring Lake High School has officially begun!

(Spring Lake, MI) May 30, 2024 – Staff at Spring Lake…